Woodside Ferry Terminal: the scale of a planned retrofit

A historical energy summary compares a 2016 baseline with modelled post-retrofit use.

Woodside Ferry Terminal energy efficiency summary with baseline, modelled usage and retrofit measures.
Woodside Ferry Terminal energy efficiency summary with baseline, modelled usage and retrofit measures. View full size (opens in a new tab)

Historical archive based on the original post’s topic and supplied image. The date is the original LinkedIn post date; earlier projects and participation are not presented as PB Energy engagements.

The supplied Woodside Ferry Terminal summary compares annual energy use of 876,447 kWh in the 2016 baseline with modelled usage of 214,000 equivalent kWh after improvements. The table presents an estimated energy reduction of 75.6%.

Listed measures include a variable refrigerant flow heating system, enhanced insulation, efficient windows, optimized ventilation, LED lighting, controls and daylighting.

The historical table also compares baseline annual energy costs of $81,072 with modelled costs of $26,000. These are projections using the assumptions of that period, not current prices or verified post-retrofit results. The project belongs to Halifax Regional Municipality.